Friday, November 26, 2021 appointment

Findings

Repair completed. Water level is 1.5ft above bottom to match ground water and keep the pool safe. Pool can be filled immediately Pump is off at the timer Valves were readjusted to their original positions

Wednesday, November 24, 2021 appointment

Findings

After a long battle with water tables today which required additional amount of material to be used to complete the main drain repair the specialists were unable to finish the repair today. The main drain has been re-plumbed and started to reseal into the shell of the pool but the specialists ran out of material before completion. This will require and extra appointment on Friday to complete the repair.